Could 17 (Renewables Now) – German funding firm CEE Group is planning to construct a 154.4-MWp photo voltaic undertaking in Brandenburg which can enhance the put in photo voltaic capability in its portfolio to 718 MWp.
The Doellen ground-mounted photo voltaic park shall be situated within the district of Prignitz and development work on the undertaking is scheduled to begin in June. The photo voltaic modules shall be delivered by producer Astronergy, beginning in August.
German firm Goldbeck Photo voltaic GmbH has been chosen because the engineering, procurement and development (EPC) contractor for the undertaking.
As soon as up and operating in March/April 2023, the photo voltaic park is predicted to supply about 150 GWh of inexperienced energy.
The Doellen undertaking shall be a part of CEE Group’s SICAV-RAIF Renewable Fund 7 (CEE RF7).
After the commissioning of the park, Hamburg-based CEE Group can have a portfolio of 1.34 GW of inexperienced energy capability, together with 622 MW of wind and 718 MWp of photo voltaic.